Work on Plant 201 Water Treatment Plant Begins

Jan 17, 2025
  • Your Utility at Work
  • Health & Safety

By: Jorge Lopez, P.E., Vice President, Engineering

The California Public Utilities Commission (CPUC) authorized Suburban to construct the PFAS removal plant at Plant 201 in December 2024. It will be the largest individual project, most expensive and most complex in Suburban’s long history. PFAS is a group of synthetic chemicals resistant to heat, water, and oils. It is known as a forever chemical because it doesn’t break down easily in the environment.

The CPUC authorized Suburban’s request of $21 million in 2025 to build the project. We estimate the total cost of the treatment plant will be more than $40 million and take more than two years to complete. The project must be completed before the Environmental Protection Agency (EPA) starts enforcement of the Maximum Contaminant Levels (MCL) for Per-and polyfluoroalkyl substances (PFAS) in 2029.

The treatment plant will remove PFAS from the groundwater produced by wells at Plant 201 that serve the Whittier-La Mirada (WLM) customers. The treatment plant’s capacity is 15 Million Gallons Per Day (MGD) and will serve as the primary source for the WLM system. 

Suburban’s Engineering Department engaged consulting engineers Carollo Engineering to design the treatment plant starting in 2020 in anticipation of EPAs MCL. Carollo is a leading global engineering firm that has extensive experience working on similar projects. The treatment plant’s design has been completed, and Ion Exchange (IX) technology was selected because it has the lowest life cycle cost for our application compared to other technology. The treatment plant will have seven sand separators, three cartridge filters, 16 media vessels (17 feet high and 12 feet in diameter), and a sophisticated Supervisory Control and Data Acquisition (SCADA) system to operate and monitor the treatment plant. 

Engineering is working with the City of Pico Rivera to obtain all necessary permits to start project construction as early as the second quarter of 2025. The first sequence of the project involves building an earthen mound to raise the treatment plant above flooding levels behind the Whittier Narrows Dam, and new piping to collect water from the wells and deliver it to the treatment plant.

We will update you on this critical project during major milestones until the treatment plant is operational. The Plant 201 Treatment Plant demonstrates Suburban’s constant commitment to ensuring a safe and reliable water supply to our community of over 120,000 people who rely on this water.

Suburban Water Systems District Offices

La Mirada and Whittier Office

15088 Rosecrans Ave
La Mirada, CA 90638 (map)

Tel (562) 944-8219
Fax (626) 543-2692

San Jose Hills Office

Ste. 100, 1325 N Grand Ave
Covina, CA 91724 (map)

Tel (626) 543-2640
Fax (626) 543-2664

Sativa Office

2015 E Hatchway St
Compton, CA 90222 (map)

Tel (310) 631-8176
Fax (626) 543-2692


Toll-Free (800) 203-5430 • TTY (877) 405-1710
Business hours are M-F, 8 AM to 4:30 PM. After hours emergency calls are transferred to on-call personnel.
District Offices are closed on Fridays.

home-610x350-utility-worker-taking-water-sample
home-slice-water-quality-bkg

Water Quality at Suburban Water Systems

We follow U.S. EPA monitoring and testing protocols to ensure your drinking water is safe.

Learn More About Water Quality
homepage-slice-baclground-water-running-into-kitchen-sink 

Learn About Your Water Service

How it safely reaches your home, and how we use it and protect it for the future is the focus of our Water 101 pages.

Learn More About Water
h2ome-water-text-slice-homepage
sws-icon_lifeline

LifeLine™

For under $7 a month, the LifeLine Maintenance Plan will cover the repair or replacement of earthquake-damaged outside water line.

Get LifeLine
sws-icon_wish-lira

CAP

Our low income Customer Assistance Program (CAP), provides a bill-reducing credit on qualifying customers’ water bills each month.

Apply for CAP
sws-icon_paperless-billing

Go Paperless

Say goodbye to paper bills, and enjoy the convenience of managing your utility account with My Account, our online self-service portal. It's fast, free, and secure.

Go Paperless